RM Campbell Indus. v. Midwest Renewable Energy, LLC

by
RM Campbell Industrial, Inc. entered into a contract with Randall Kramer for construction work on an ethanol plant. The terms of the contract indicated that the contract was between Campbell and KL Process Design Group, LLC. Midwest Renewable Energy, LLC, paid the invoices. When Midwest stopped making payments and KL Process ceased work on the project, Campbell filed suit against Midwest for breach of contract. After a trial, the jury found for Campbell in the amount of $154,510.98. The Supreme Court affirmed, holding that the district court did not err in (1) concluding that there was sufficient evidence for a jury question in whether KL Process acted as an agent of Midwest in entering into the subcontract with Campbell and whether there was an enforceable contract between Midwest and Campbell; and (2) not finding that Campbell had to prove substantial compliance with the subcontract and not instructing the jury on this. View "RM Campbell Indus. v. Midwest Renewable Energy, LLC" on Justia Law